Raymond — thanks for the bid. The pricing looks good.
Before I send the final Project Sign-Off for electronic signature, I want to confirm the 15 items below that were not clearly listed on your original bid. For the standard items, mark Yes if they are included in your original $59,522.00 quote, or No if they are excluded or would add to the price. Item 9 reflects the rock condition already encountered and the separate $2,500.00 hammer adjustment already approved by TruLot.
Approved price adjustment to date: Rock has already been encountered. TruLot has approved an additional $2,500.00 for hammer work, bringing the current approved project total to $62,022.00. Additional rock conditions may require additional work and cost. Any additional rock-related charge beyond the $2,500.00 approved to date must be submitted to TruLot and approved in writing before the additional work proceeds.
After confirming the 15 items above, review the complete Scope of Work for the project. This document is the full project scope that your quote is being confirmed against.
Open Full Scope of Work (PDF)